Bleckmann - Pallet racking storage system

Pallet storage construction while operations continue

Within 8 weeks, stow delivered and installed a Pal Rack® pallet racking system for Bleckmann in the UK. The installation is 12 metres high and helped create no less than 12600 picking levels.

Bleckmann - Pallet racking storage system

Bleckmann is a leading logistics provider serving various clients, stretching from fast growing online-first retail brands up to well-established international players, particularly in the fashion and lifestyle industries. Their distribution centres are spread across the Netherlands, Belgium and the United Kingdom, with a local presence in the United States.

stow has been a major supplier of Bleckmann for years, with a number of successful projects done in the UK. Bleckmann considers stow to be a front-runner in the logistics field. 

The project was carried out in the Bleckmann warehouse in Bury St. Edmonds (UK). 

transparent placeholder

There were several major challenges to overcome:

Warehouse operations continued during the installation of the new system and orders were still being shipped out to customers.

From a health and safety point of view, everything needed to run smoothly and safe, given that it was a construction site.

The biggest challenge, however, was completing the project within the specified time. “If you consider the conditions under which we carried out the work, it was quite a challenge,” says Neil Robbins, Project Manager with stow UK.

Within 8 weeks, stow delivered and installed a Pal Rack® pallet racking system. The installation is 12 metres high and helped create no less than 12600 picking levels in a VNA (very narrow-aisle) operation with single sided 1200 mm deep racks, hand loaded with boxes from both sides from man-lifting trucks.

stow was able to deliver the project in-time and within budget.

It was a task done in impossible conditions and with an impossible timeline.”

Sven Amerijckx, Sales Director, stow UK

The stow project manager on site was very co-operative and constructive and the collaboration with the local Bleckmann team was excellent.

Mark Noblett, Project Manager, Bleckmann

stow was able to deliver the project in-time and within budget.

Mark Noblett, Project Manager, Bleckmann